Stone, Stone, and More Stone

We had 9 loads of stone delivered today -- 202 tons to backfill and bring the interior up to grade for the slab.  We are having it spread out right now, and I'll load some pictures of that afterward...

We will also have the forms off the last of the foundation wall a little later, also...

We were able to get most of the tiling in for drainage for the downspouts, and some 4" PVC down into that tiling.  It isn't finished yet, but will be later -- when the rest of the forms have been removed...

I also had my electrician come out this morning and put some conduit through the sleeves to bring the conduit up a bit so they don't have to do quite so much digging when it's time to put those in...  I'll leave the drain open so my plumber can access it without too much trouble also...