Monday, March 2, 2009

Plumbing Rough-In Inspection Done!

Well, today, Wren's Plumbing completed connecting up the manifold to the well pressure tank and the hot water heater, etc.  There are valves before the manifold which are still turned off, but the water is turned on to the water heater -- which is now filled...  The power for the water heater will be connected tomorrow morning, and then we'll have hot water!

We also got the plumbing inspection completed today, so that is a major milestone!  We are very nearly ready for the framing and electrical rough-in inspection.  I have some low-voltage wiring to at least start prior to that, and then we will get that inspection done.

After the inspection and wiring are done, then I can put up the insulation in the ceiling, and then we can finally get the heat turned on!  It may be past the cold by then, but it will still be another major milestone!

No pictures today...  Nothing much new to take pictures of...

No comments: